  • Baixo Iguaçu Hydroelectric Power Plant Third Generating Unit starts operating

    DATE: 03/27/2019

    Published by: OEC

    The third and last generating unit at the Baixo Iguaçu Hydroelectric Power Plant (HPP), located on the Iguaçu River in Paraná, started operating this Thursday, March 21. The Kaplan turbine for the 3rd unit was completed before the contract deadline and has the capacity to generate up to 116.7 MW.

    The project, which began in 2013, is nearing completion. With the main stages of the civil works and assembly finalized, the teams will now focus on following-up and undertaking services that will ensure a complete handover of the hydroelectric power plant to the client, the Baixo Iguaçu Entrepreneurial Consortium (Neoenergia and Copel).

    One of the energy ventures of lower environmental impact in the country, the Baixo Iguaçu HPP now has 350.2 MW of installed power, enough to serve one million people.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0
    OEC

    On March 13 and 20, the  SENAI held two meetings as part of a program to create and validate...

    March 27, 2025
    +
    0
    OEC

    On March 19th, members of the OEC’s Engineering and Innovation department had the opportunity to take part in a...

    March 26, 2025
    +
    0
    OEC

    Did you know that Novonor has launched a chatbot to make it easier for members to access the content...

    March 20, 2025
    +
    0
    OEC

    On March 18, the first meeting of the Heavy Construction Committee was held in São Paulo, an integrated action...

    March 20, 2025