  • Guaratuba Bridge Reaches 65% Completion

    DATE: 07/29/2025

    Published by: Odebrecht Engineering & Construction

    The construction of the Guaratuba Bridge, being carried out by Odebrecht Engineering & Construction on the coast of Paraná, has reached 65% completion. One of the highlights of the project, which is being executed by the Department of Roads and Highways (DER/PR), was the progress of the cable-stayed section structure.

    Over the past month, the starting segments that support the main towers were completed. Additionally, a total of 54 piles have been concreted in the bay so far. The production of precast longitudinal beams also continued, with 105 structures manufactured and 88 already installed on the crossbeams.

    The bridge is being built along the PR-412 highway, and its full length of 3.07 km lies within the municipality of Guaratuba. However, the project includes access points at both ends, referred to as the Matinhos side and the Guaratuba side. The Guaratuba access section is approximately 951 meters long, while the Matinhos side is about 875 meters in length.

    Structure

    The bridge will have over 1,200 meters and will feature four traffic lanes, two safety lanes in each direction, sidewalks with a bike path, and guardrails—offering greater safety and comfort for residents and visitors to the coast.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0

    Odebrecht Engineering & Construction held the third edition of the BIM Workshop on July 15 and 16. The initiative...

    July 24, 2025
    +
    0

    On July 2nd and 3rd, the People and Organization team of Odebrecht Engineering & Construction was present at the...

    July 22, 2025
    +
    0

    On June 10, 11, and 12, 2025, was held in São Paulo the 12th International Compliance Congress, organized by...

    July 02, 2025
    +
    0

    The Municipal Government of Soledade (RS), the SENAI, and the ViaSul Construction Consortium – formed by the construction companies...

    June 30, 2025