  • First phase of AH Laúca Transportation System concluded

    DATE: 10/31/2018

    Published by: Odebrecht Engineering & Construction

    In October, the Laúca Hydroelectric Project commemorated the conclusion of the first phase of the Transportation System project associated with AH Laúca. The hydropower plant, which is the largest project of Odebrecht Engineering & Construction in Angola, accounts for 40% of all the power produced in the country’s North System.

    The project includes 305 km of 400 transmission lines installed and already in operation out of a total of 750 km to be delivered by 2020.

    This first phase included the lines Laúca-Capanda (40 km), Laúca-Cambutas (75 km) and lastly Laúca-Catete, for which a 190-km transmission line was built, which resulted in the expansion of Substation 400 kV in Catete.

    “The Laúca-Catete Transmission Line, which will improve the reliability of Angola’s power grid, will have the capacity to distribute the power produced by AH Laúca directly to the city of Luanda, thereby expanding the supply of electricity,” explained Leonardo Oikawa, manager of the project’s Transmission Lines.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0

    Odebrecht’s Internal Audit department held the first edition of AuditNext – Brazilian Internal Audit Meeting on May 28 at...

    June 09, 2026
    +
    0

    Tenenge, in partnership with Instituto Banco Vermelho (IBV), is promoting a series of awareness initiatives to combat violence against...

    May 29, 2026
    +
    0

    Odebrecht’s Innovation department held, this Thursday (28), starting at 6:00 p.m., at Inovabra—the Bradesco innovation ecosystem—the launch of its...

    May 29, 2026
    +
    0

    A group of approximately 50 residents from the area surrounding the Gávea Station construction site, including representatives from the...

    May 25, 2026