  • Minérios Highway (PR) reaches 70% completion

    DATE: 06/16/2025

    Published by: Odebrecht Engineering & Construction

    The concrete duplication of the Minérios Highway(PR-092) in Almirante Tamandaré, Metropolitan Region of Curitiba, reached 70.03% completion last month. The project, executed by Odebrecht, is managed by the Paraná Department of Highways (DER/PR).

    The work extends from km 14.3 to km 15.6 of the highway, which equals 1280 meters in length. Vehicle traffic was recently diverted to the marginal roads in a new section, allowing the progress in the execution of the rigid concrete pavement on the central lane. There will be four traffic lanes, two in each direction.

    In addition to the concrete duplication, other ongoing services in the section include the paving of the marginal roads, the implementation of the water drainage system, pedestrian walkways, bike paths, and containment devices, which will be followed by new signage, the completion of road lighting, and other complementary services.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0

    Construction on the Northern Section of the Mario Covas Ring Road (SP-021) is progressing rapidly and recently reached two...

    September 04, 2025
    +
    0

    From August 29 to 31, the SOS Caatinga Institute held the 8th edition of the event “48 Hours of...

    September 03, 2025
    +
    0

    In August, young people from Soledade (RS) attended the inaugural class of the Industrial Logistics Process Operator course, promoted...

    September 03, 2025
    +
    0

    Between June and August of this year, the Campo Grande Ring Road project promoted a visitation program to its...

    September 02, 2025