  • Campo Grande Ring Road Works Enter Final Stage

    DATE: 11/17/2025

    Published by: Odebrecht Engineering & Construction

    In recent days, the works on the Campo Grande Ring Road have advanced through decisive stages with the completion of the installation of 35 beams, totaling 8 spans, the concreting of the first slabs, and the start of construction on the Posse Roadway.

    The installation of beams on spans 4 and 5 was a complex operation carried out over three days due to the proximity of Light’s high-voltage poles. This activity required rigorous planning, mobilization of two high-capacity telescopic cranes, special trailers, and a highly qualified team to ensure safety and precision. In spans 4 and 5 alone, 8 beams measuring approximately 29 meters each were installed. The activities were performed at night to minimize traffic impacts.

    Interventions on Estrada da Posse for the start of the Posse Roadway works also demanded detailed planning and an integrated operation with public agencies, ensuring broad communication of the stages to maintain circulation without affecting the main traffic flow, preserving mobility for vehicles, pedestrians, and residents.

    Additionally, strategic sections such as Rua Minas de Prata, the Luiz Bom Tunnel, and the Via Expressa Light have also been completed. These works are essential to connect Estrada da Caroba to Estrada da Posse and create a new mobility dynamic in the region.
    With the completion of the Viaduct and the Posse Roadway, Campo Grande will gain new routes, improved traffic flow, reduced travel times, and greater safety and comfort for drivers and pedestrians.

    This is one of the largest urban infrastructure projects in Brazil’s biggest neighborhood, marked by technical and logistical challenges that required innovation, coordination, and dedication.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0

    The duplication works on the E/Lajeado Section of BR-386, carried out by the Via Sul Construction Consortium (CCVS) and...

    January 30, 2026
    +
    0

    As construction at the Gávea subway station advances to the stage involving the detonation of 60 meters of rock,...

    December 16, 2025
    +
    0

    The Young Builder class, a global program by Odebrecht Engineering & Construction aimed at developing young leaders and specialists,...

    December 04, 2025
    +
    0

    On November 25, the Learning area of Odebrecht Engineering & Construction’s HR department and PPP Saúde BH’s Project Manager,...

    December 03, 2025