  • Consortium with OEC participation will build 1.2 km bridge in Paraná

    DATE: 11/18/2022

    Published by: Odebrecht Engineering & Construction

     R$ 386 million contract provides for the execution of Guaratuba road, improvements in the surroundings and access to the city on the coast of Paraná.

    OEC – Engenharia e Construção through the Nova Ponte Consortium will act in the planning and execution of Guaratuba Bridge, on the coast of Paraná (PR). The announcement of the bid valued at R$386.9 million was made by the DER/PR (Paraná’s Department of Highways). With a length of 1.2 km, the road will have four lanes for vehicles. Besides the construction of the structure, the project provides for improvements in the surroundings and in the access roads, contemplating the widening of PR-412 highway and the connection with Tabaquara Road to the city of Matinhos.

    The forecast is that the construction will be executed within 32 months, considering the time for the environmental permits (two months), the project preparation (six months) and the construction services (24 months). The consortium is formed by: OEC (50%), Carioca Christian-Nielsen Engenharia S.A. (25%) and Goetze Lobato Engenharia S.A. (25%), all companies with a wide range of experience in large projects.

    The bridge will be 1,244 meters long, with a minimum width of 22.60 meters, and will be built using three construction methods for the superstructure: cantilevered span, cantilevered succession, and precast beams. Four traffic lanes of 3.6 meters each, two safety lanes of 60 centimeters each, rigid concrete New Jersey barriers of 40 centimeters, sidewalks with bicycle lanes on both sides, 3 meters wide, and 10 centimeters of guardrail at the ends of the bridge are planned.

    No comments

    Want to learn more
    about the subject?

    Click here and leave you suggestion
    for the next post

    Related news

    +
    0

    In reference to the month dedicated to suicide prevention awareness, Yellow September, Odebrecht Angola’s projects promoted various actions to...

    October 03, 2025
    +
    0

    The company reached a revenue of R$ 5.2 billion in 2024, marking a 48% growth compared to the previous...

    October 02, 2025
    +
    0

    With the growing energy demand and the transition to intermittent renewable sources such as solar and wind, the Brazilian...

    October 02, 2025
    +
    0

    Last September, interns from the DS Angola office had the opportunity to put into practice the theoretical knowledge they’ve...

    October 02, 2025